PUBLICATION OF THE AWARD OF CONTRACT
Name of Project: Disaster Vulnerability Reduction Project
Procurement of Works- Micoud Secondary School
SLU-DVRP-W-NCB-MSS-01-19
a) Names of each Bidder who submitted a Bid
b) Bid Prices as read out at Bid Opening
Name of each Bidder who submitted a Bid |
Bid Prices as Read Out at Bid Opening XCD |
OB Sadoo Engineering Services Ltd. |
$6,162,004.45 |
Mega Contracting Inc. |
$6,330,346.56 |
Contruction and Industrial Equipment Ltd. |
$4,992,217.06 |
Cepal Holdings |
$5,470,000.81 |
Qingdao Fuhaiyang Construction Group Co. Ltd. |
$6,589,477.96 |
Triple "L" Company Ltd. |
$6,416,300.63 |
Nanjing Xingye Construction Ltd |
$3,623,345.00 |
c) Name and evaluated prices of each bid that was evaluated
Bidder |
Evaluated Bid Prices - XCD |
OB Sadoo Engineering Services Ltd. |
$6,932,255.01 |
Mega Contracting Inc. |
$7,121,639.88 |
Contruction and Industrial Equipment Ltd. |
$6,301,618.62 |
Cepal Holdings Inc. |
$5,818,440.69 |
d) Names of bidders whose bids were either rejected as non responsive or not meeting the qualification criteria or non evaluation
Bidder |
Reasons for Rejection of Bid |
Qingdao Fuhaiyang Construction Group Co. Ltd. |
• Bid did not comply with ITB ll.l(a) and ITB ll.l(e) |
Triple "L" Company Ltd. |
• The project referred to in the Letter of Bid is incorrect. • Bid did not comply with the requirements of ITB ll(a) |
Nanjing Xingye Construction |
• Letter of Bid does not comply with ITB ll.l(a), ITB ll.l(e) and ITB 12 • Supporting documents were note submitted to substantiate the Bidders qualifications as per ITB 17 |
e) Name of the winning bidder, and final total contract price, as well as the duration and summary scope of the contract.
Name: Cepal Holdings Inc.
Final Contract Price: XCD 5,818,440.69
Duration of Works: Fifteen (15) months
The works consist of:
The site is located at Micoud,Saint Lucia and is defined in drawings No. A-100 -101
Debriefing
Any Bidder who wishes to ascertain the grounds on which its bid was not selected, should request an explanation from the Project Coordination Unit at the address indicated below. A response in writing shall be provided explaining why such bid was not selected. If a bidder requests a debriefing meeting the bidder shall bear all the costs of attending such a debriefing meeting.
Attention: The Project Coordinator
Project Coordination Unit
Disaster Vulnerability Reduction Project
Department of Economic Development, Transport and Civil Aviation
2nd Floor, Finance Administrative Centre, Point Seraphine,
Castries
Saint Lucia
Email: slupcu@gosl.gov.lc
Tel: 468 -2413